Not sure if anyone has seen this. We have just recently upgraded from SV1(2) to SV1(3a) in order to support 4.1. We also rebuilt our vcenter server, and seem to be having a strange issue where the sync status is stuck "in progress".
N1KV-VSM1(config-svs-conn)# sh svs connections
connection vcenter:
ip address: x.x.x.x
remote port: 80
protocol: vmware-vim https
certificate: default
datacenter name: Datacenter
DVS uuid: 22 ea 3a 50 ed 7a 7e 6e-43 f8 c2 f8 3c 06 97 62
config status: Enabled
operational status: Connected
sync status: in progress
version: VMware vCenter Server 4.1.0 build-258902
If I attempt to perform a "no connect" and "connect", I see the following error -
N1KV-VSM1(config-svs-conn)# no connect
SVS connection service is busy. Please try again later.
Has anyone experienced this? Resolutions?